10th May 2019
Dear Supporters,

Thank you for your support. As I have mentioned during the construction of road a Hard rock was in middle which has to cut completely and it took more than 1.5 months to connect both edge.
Dear Supporters,

Thank you for your support. As I have mentioned during the construction of road a Hard rock was in middle which has to cut completely and it took more than 1.5 months to connect both edge.
20th March 2019
Dear Supporters,

Thank you for your love. Sorry guys, for late update. Following are some latest progress of road.



Villager's are working hard to complete this as soon as possible.


 
Dear Supporters,

Thank you for your love. Sorry guys, for late update. Following are some latest progress of road.



Villager's are working hard to complete this as soon as possible.


 
20th February 2019
Work progress:


There is approx 150-200 meter pending work only for JCB, but as it's hard ROCK so we had to get another JCB to crack it which still seems to be difficult. We need to get another machine which is costly due to transport cost.
Work progress:


There is approx 150-200 meter pending work only for JCB, but as it's hard ROCK so we had to get another JCB to crack it which still seems to be difficult. We need to get another machine which is costly due to transport cost.